Executive summary
The Brighton & Hove City Council Permit Scheme (B&HPS) was introduced on 30th March 2015 and had a successful first 3 years with a steady increase in the volume of works managed by the scheme. This was effectively managed by the team and managers via forward planning, recruitment, and training.
Year 1, 2 and 3 were individually evaluated and reported on in line with the DfT requirements. Years 4 to 6 were evaluated as a single 3-year report in line with the DfT requirements. This report is another 3-year evaluation and covers years 7 to 9 from the 1 April 2021 to the 31 March 2024, again, in line with the DfT requirements.
The purpose of this report is to evaluate the impact of the Permit Scheme, its operational performance and consider the fee structure, the costs, and benefits of operating the scheme and whether the Permit Scheme is meeting key performance indicators where these are set out in the Guidance.
The Permit Scheme is not intended to prevent activities necessary for the maintenance or improvement of the road network or the services running underneath it.
It is designed to make available the necessary resources to achieve an appropriate balance between the interests of the various parties and where possible, bring about effective co-ordination between all the different competing interests.
There are a wide range of indicators and measures that the industry has been discussing and agreeing that should be reported on.
Some of these are possible to report on and some require further work or system changes to prepare. This evaluation identifies all the indicators and measures agreed by the industry and various representative groups.
Although some data is not available currently, the requirement and format has been documented in this evaluation so that it can be identified easily and worked on over following years.
When the B&HPS was being developed, a Benefit to Cost Ratio was prepared using predicted costs and volumes of applications and an DfT assumed 5% reduction in works impact.
Now there are actual costs and actual works volumes and durations, this has been rerun using the same DfT 5% assumed reduction in works impact, base line societal costs of works and today’s actual scheme operating costs.
Permit scheme cost benefit analysis results
Year 7
- Costs - £774,792
- Benefit - £8,437,974
- Benefit to Cost Ratio - 10.89:1
Year 8
- Costs - £829,505
- Benefit - £8,603,066
- Benefit to Cost Ratio - 10.37:1
Year 9
- Costs - £848,562
- Benefit - £7,900,040
- Benefit to Cost Ratio - 9.31:1
Permit scheme performance report
It is important to note that during the past 3 years there has been ongoing major IT system developments regarding the integration of the DfT’s Street Manager system and a variety of existing systems and interfaces have been developed and deployed.
This has resulted in many gaps in the data seen below and throughout this report. This situation continues to resolve itself resulting in increased data allowing increased analysis and management focus. This ongoing improvement can already be seen in the data below.
During years 7 to 9 of operation of the Permit Scheme Permit applications received from Utility Promoters and Highway Authority Promoters has gradually begun to decrease from 19,774 to 16,264.
Authority applications have grown from 2,869 in year 7 to 4,664 in year 9. This could be linked to the changes in council contracts, that have meant that permit applications have increased. In this time we also had fibre rollout within the City which equated to a large amount of works.
Utility applications have reduced from 19,905 in year 7 to 11,600 in year 9. This is a common position developing nationally and primarily a result of the broadband rollout being delivered.
This total includes applications that were granted but subsequently cancelled by the Promoters before the works were undertaken.
On average, a consistent 80% to 90% of applications were from Utilities, which is an industry consistent figure, and an average of 80% were granted each year.
15% of applications were from the Highway Authority in years 7 and 8 and this percentage has grown in year 9 to 29% as Authority volumes have increased and the Utility volumes have decreased.
Circa 87% of Authority applications were granted and circa 80% of Utility applications were granted. There is an expectation that Authority applications will be granted as a slightly higher rate as they come from within the organisation. This is a clear indicator of Parity of treatment.
The number of applications Deemed, which is automatically granted due to no response by the permit team, has remained consistently very low at less than 1%.
Permit Variation volumes are consistent and are granted at a rate of between 75% and 89%.
Varying Permits as opposed to refusing them is an effective co-ordination process demonstrating a dialogue between the Permit Team and Promoters to ensure the works cause the minimum disruption possible. Substantially high volumes of Variations is seen across the industry now that the process managing Permits is better understood and delivered.
The average individual Permit cost to Promotors was £44 and a figure seen across the industry. The expected range is £30 to £50.
Average durations of Major Utility Works have varied from 5 to 12 and appear to be increasing.
Average durations of Major Authority Works are consistently 13 to 14 days over the 3 years due to the larger scale type of works undertaken.
Conditions attached to granted permits has grown, partly in line with volume increases and ongoing improvements in the consideration of the works proposals. In addition, there are now additional requirements for conditions to be included in all applications, principally regarding ‘Consultation and Publicity’. This is a clear indication of the ongoing improvement in the consideration of the impact of works and the subsequent discussions and agreements with Promoters being reached to minimise their impact.
Inspections to monitor compliance with the Conditions attached to granted permits has grown and fallen back, partly in line with volume increases and decreases, however, generally there has been substantial growth in inspections due to business process improvements and staff availability.
This level of monitoring and identification of non-compliance is a very positive result, and another clear indication of the ongoing improvement being made in managing the scheme.
There was a total of 447 Utility Permit breaches in year 7, 341 in year 8, and 401 in year 9. This is an increase over recent years and partly reflects increased volume along with increased monitoring of compliance. The impact and effectiveness of the Permit Scheme is reliant on compliance with requirements so is a critical area to maintain focus on.
Years 7 to 9 issues
The Broadband rollout has impacted the industry enormously and has continued over the past 3 years. However, the Brighton & Hove Permit Team’s ability to deliver the full range of permit functions during this period of turmoil is an outstanding achievement by the whole team and their managers. The years have seen ongoing management and operational improvements across a range of measures, detailed above and in the tables below.
The IT system’s ability to produce reports consistent with the industry’s agreed indicators and measures has been a major problem, however, improvements can already be seen in the data recorded in this report and will continue to improve over time.
Historically, the industry has agreed on a range of reports that none of the system providers have been able to produce. The central government initiative to develop a new single central IT system called Street Manager is replacing current providers and will hopefully clarify KPI and management reporting requirements in future years.
Staff
The Permit Scheme staffing level has continued to increase due to the number of permit applications that need to be managed.
The Permit Scheme is fully resourced, and this is expected to continue.
Actual operational requirements and operating costs are now better understood and fully accounted for.
Operational costs
Operational costs are higher than original budget figures due to higher than anticipated volumes of work and inflationary cost increases.
Conclusions
This report provides evaluation findings of key indicators and measures for the Brighton and Hove Permit Scheme after its seventh, eighth and ninth year of operation.
The Consultant rates the Brighton and Hove Permit Scheme as Excellent.
One of the most impressive achievements is that Permit applications have continued to grow and then reduced during the past 3 years, yet Deemed Permits (automatically granted when not assessed by the Permit Team) has remained below 0.5%.
Considering the fluctuation on works volumes and the increasing in operations such as compliance monitoring, the Permit Scheme has been delivered very well with ongoing improvements delivered by management and the team year on year.
There are several key improvements seen in over the 3 years including continuous improvements in the volume of conditions attached to works, ongoing inspections of works against a backdrop of volume increases, effective revenue and cost management and delivery of parity of treatment between Utility and Authority promoters. This is all critical to the permit scheme achieving its objectives of managing works and minimising their impact.
The team consistently co-ordinate all road and street works in Brighton & Hove and take the time to review every application and apply conditions to minimise the impact of the works on the users of the network.
Income is expected to be in line with scheme operational costs going forward. Therefore, there is no need to consider an adjustment in fee rates to ensure costs and income are balanced over the coming several years.
There are still some difficulties gathering accurate data from the IT system, but this has improved, and is expected to continue to improve over the following years.
The Permit team and Promoters will continue to work together and make improvements to minimise the impact of works on the highway network.
Works are being Permitted and co-ordinated effectively, especially considering the work volume demands from the rollout of the fibre broadband.
The entire network is being managed to the best of the team’s ability with the tools and resources available to them and is a considerable achievement and worthy of praise.
Looking forward
The Permit Scheme will continue to maintain its effectiveness over the following years with a focus on these key areas.
- Consider a Lane Rental Scheme to reduce works busy period durations and better align the charges for works with the cost of the disruption they cause.
- Update and maintain an accurate Traffic Sensitive Streets list as a key
- Monitor the DfT’s new Street Manager system and feedback the need to improve data recording and reporting.
- Continuing staff recruitment, training, and development to maintain the required staff levels and skills.
- Consider how the Permit Team can support other initiatives within the highways area such as programmes to assess the level of compliance with Specification of the Reinstatement of Openings in Highways (SROH).
- Consider how the team can respond to Brighton & Hove City Council declaring a climate and biodiversity emergency in 2018 and its commitment as a city to become carbon neutral by 2030.
Developing the permit scheme
During 2013 and after an initial high-level financial assessment, consideration of the local needs and discussion with internal stakeholders, operational partners, consultants and neighboring Highway Authorities, Brighton & Hove City Council has decided that the most appropriate scheme for Brighton & Hove is one that would operate on all streets.
The Brighton & Hove Permit Scheme has been designed to assist the Council to manage the existing local road network for the benefit of all road users. The Permit Scheme will support existing activities and priorities of the Council and will provide a positive benefit. The Scheme will also encourage the undertakers, including those working for and on behalf of the Highway Authority to work in collaboration.
The Permit Scheme has been operationally and proactively focused on Strategically Significant Streets and to further the overall cultural shift to better management of the network. However, co-ordination of all activities on all streets will be undertaken to deliver effective and proactive management of the entire network and consider the needs of all highway users and stakeholders such as local community bus operators.
Lower fees will be charged for activities on non-traffic sensitive streets and category 3 and 4 roads.
Discounted fees will also be given in the following circumstances:
- Where several Permit applications for works that are of part of the same project but which are carried out on more than one street, but on a scale comparative to one street, are submitted at the same time.
- Where several Promoters are working within the same site submit applications at the same time. Where the Highway Authority Promoter is collaborating with Statutory Undertakers, those Undertakers will be eligible for the discount.
- Where works are undertaken wholly outside of traffic sensitive times on Traffic Sensitive Streets. The improvements in the planning processes will benefit the operational management of the road network and undertakers needing to carry out works.
Permit scheme objectives
The objectives of the Brighton & Hove Permit Scheme are:
Working together to deliver a safe, efficient, and sustainable highway network for everybody
All activities on highways have the potential to reduce the width of the street available to traffic, pedestrians and other users and have the potential to also inconvenience businesses and local residents.
The scale of disruption caused is relative to the type of activities being undertaken and the capacity of the street. Activities where the traffic flow is close to, or exceeds, the physical capacity of the street will have the potential to cause congestion, disruption, and delays.
The key objective of the Brighton & Hove Permit Scheme is to improve the strategic and operational management of the highway network through better planning, scheduling and management of activities to minimise disruption to any road or pavement user.
The Brighton & Hove Permit Scheme will enable better co-ordination of activities throughout the highway network, ensuring those competing for space or time in the street, including traffic, to be resolved in a positive and constructive way.
The objectives and benefits of the Brighton & Hove Permit Scheme are:
- reduced disruption on the road network
- improvements to overall network management
- a reduction in delays to the travelling public
- a reduction in costs to businesses caused by delays
- promotion of a safer environment
- reduced carbon emissions
The Permit Scheme objectives will be facilitated by improving performance in line with the Authorities' Network Management Duty in relation to the following key factors:
- enhanced co-ordination and cooperation
- encouragement of partnership working between the Permit Authority, all Promoters, and key stakeholders
- provision of more accurate and timely information to be communicated between all stakeholders including members of the public
- promotion and encouragement of collaborative working
- improvement in timing and duration of activities particularly in relation to the busiest streets within the network
- promotion of dialogue with regard to the way activities are to be carried out
- enhanced programming of activities and better forward planning by all Promoters
Aligned objectives
The Permit Scheme objectives align with the strategic objectives contained within the Brighton & Hove Local Transport Plan 3 Part B Delivery Plan:
- being innovative and creative
- providing and using accurate/robust information
- involving partners, stakeholders, and communities
- ensuring integration and coordination
The implementation of the Permit Scheme was financially justified in the Cost Benefit Analysis produced during the design and consultation phase and was based on an assumption, required by the DfT, that it would produce a 5% reduction in roadworks.
Appendix 1: Evaluation background
Permit scheme evaluation
Swift Argent Ltd was commissioned by Brighton & Hove City Council (B&HCC) to evaluate the performance of the B&HPS as a requirement set out in The Traffic Management Permit Scheme (England) (Amendment) Regulations 2015 regulation 16A.
The B&HPS was implemented on 30th March 2015 and the purpose of this report is to gather and analyse data and to evaluate the Permit Scheme and consider the fee structure, the costs, and benefits of operating the Scheme and whether the Permit Scheme is meeting key performance indicators where these are set out in the Guidance.
Scope of work
In order to evaluate the performance of a Permit Scheme a number of data items are required to enable analysis.
Data is available within the street works IT system along with financial information from the Authority finance department.
The individual data items are set out later in this report for each indicator but will include the following categories.
- Number of Permits granted, modified, refused and varied
- Parity of treatment between Utilities and Authority works
- Conditions attached to Permits and breaches
- Variations and extensions and early starts
- Inspections carried out and results
- Works durations
- Customer enquiries
- Permit fees
- Operational costs
- Societal benefits
Report structure
- Executive Summary
- Cost Benefit Analysis
- Permit Scheme Performance
- Evaluation Background
- Key Performance Indicator Data
- HAUC TPI Measures
- Authority Measures
- Costs and Income
Key performance indicators
A set of Key Performance Indicators (KPIs) and Objective Measures (OMs) are set out below to demonstrate parity of treatment between works for road purposes and street works undertaken by statutory undertakers.
Section 20.3 of the Permits Code of Practice states that every Authority that wants to run a Permit Scheme must explain how it intends to demonstrate parity of treatment for promoters in its application.
The Code contains seven KPIs that could be used for this purpose. The recording of KPIs 1 and 2 is a mandatory requirement of all Permit Schemes.
Authorities should select at least two others which they consider will demonstrate parity across their Permit Scheme. Authorities can also include their own KPIs.
- KPI 1 The number of Permit and Permit variation applications received, the number granted, and the number refused. (Breakdown of the data into applications granted and refused in relation to highway authority works for road purposes and works by utility promoters and provide a comparison with the percentage of Permits granted. Also, the data is further broken down by activity type into applications granted and refused.)
- KPI 2 The number of conditions applied by condition type.
- KPI 3 The number of approved extensions
- KPI 4 The number of occurrences of reducing the application period (early starts).
- KPI 5 The number of agreements to work in Section 58 and Section 58A restrictions. (Details of Section 58 and 58A restrictions will be provided as required under Section 8.3 of the TMA Code of Practice for Permits.)
- KPI 6 The proportion of times that a Permit authority intervenes on applications
- KPI 7 Number of inspections carried out to monitor conditions
The Statutory Guidance for Highway Authority Permit Schemes October 2015 set out TMA Permit Indicators (TPIs) for Permit Schemes are additional to the general TMA Performance Indicators, which are already being produced. The TPIs focus on occupancy, co-ordination, and inspections, and therefore relate mainly to the stages of the works from works start to final conclusion. These additional Permit indicators focus more on the process of Permit applications and responses, prior to the works being carried out.
- TPI1 Works Phases Started (Base Data)
- TPI2 Works Phases Completed (Base Data)
- TPI3 Days of Occupancy Phases Completed
- TPI4 Average Duration of Works Phases Completed
- TPI5 Phases Completed on time
- TPI6 Number of deemed Permit applications
- TPI7 Number of Phase One Permanent Registrations
In addition to DfT KPIs and HAUC TPIs. The authority can collate its own data. These measures should reflect the business case and objectives put forward in the Scheme submission documentation.
- AM 1 Average duration of works by Permit type (Included in report)
- AM 2 Inspections (% age of total undertaken and failures) (Included in report)
- AM 3 Days of Disruption Saved/ Number of collaborative works (Included in report)
- AM 4 Response Code – broken down by promoter (Included in report)
- AM 5 FPNs (Permit Breaches) (Included in report)
- AM 6 Levels of Customer Enquiries (Included in report)
- AM 7 Average Journey Times
- AM 8 Journey time reliability
- AM 9 Road Traffic Collisions
- AM 10 Carbon Emissions
- AM 11 Profit/Loss (Included in report)
| Permit | Fee - Road Category 0 to 2 or Traffic-sensitive | Fee- Road Category 3 to 4 and non-traffic-sensitive |
|---|---|---|
| Provisional Advance Authorisation | £105 | £75 |
| Major works – over 10 days and all major works requiring a traffic regulation order. | £240 | £75 |
| Major works – 4 to 10 days | £130 | £75 |
| Major works – up to 3 days | £65 | £45 |
| Standard works – between 4 and 10 days | £130 | £75 |
| Minor works – 3 days or less | £65 | £45 |
| Immediate works – Emergency Works, which are defined in Section 52 of NRSWA | £60 | £40 |
| Permit Variations – the need to alter the original plan | £45 | £35 |
Appendix 2: Key Performance Indicator (KPI) 1 - Number of permit and permit variation applications received, granted, and approved
Table 3 below shows a breakdown of Permit applications received granted and refused. This excludes Provisional Permit Applications (PAAs).
Data on Applications and Variations that are superseded is being removed from this and future reports as applications and variations applied for and granted is the meaningful data.
Data is further broken down into Permit applications received, granted and refused related to Highway Authority works and Utilities works on Table 4 below.
The number of permit and permit variation applications received, the number granted and the number refused and deemed
| Total Applications Received | 19,774 |
|---|---|
| Total Variations Received | 3,092 |
| Applications Granted | 15,231 (77%) |
| Variations Granted | 2,308 (75%) |
| Applications Refused | 4,047 (20%) |
| Variations Refused | 334 (11%) |
| Applications Deemed | 85 (<1%) |
| Variations Deemed | 49 (1.58%) |
| Total Applications Received | 19,608 |
|---|---|
| Total Variations Received | 3,610 |
| Applications Granted | 15,529 (79%) |
| Variations Granted | 3,221 (89%) |
| Applications Refused | 3,032 (15%) |
| Variations Refused | 330 (9%) |
| Applications Deemed | 49 (<1%) |
| Variations Deemed | 20 (<1%) |
| Total Applications Received | 16,264 |
|---|---|
| Total Variations Received | 4,128 |
| Applications Granted | 14,260 (88%) |
| Variations Granted | 3,787 (92%) |
| Applications Refused | 2,035 (13%) |
| Variations Refused | 261 (6%) |
| Applications Deemed | 36 (<1%) |
| Variations Deemed | 10 (<1%) |
Permit Applications by Promoter
| Permit status | Number | Percentage |
|---|---|---|
| Highway Authority Total Permit Applications | 2,869 | 15% |
| Utility Total Permit Applications | 16,905 | 85% |
| Highway Authority Total Applications Granted | 2,577 | 90% |
| Utility Total Applications Granted | 12,654 | 75% |
| Highway Authority Total Applications Refused | 277 | 10% |
| Utility Total Applications Refused | 3,770 | 22% |
| Highway Authority Total Permit Variations | 372 | 12% |
| Utility Total Permit Variations | 2,720 | 88% |
| Highway Authority Total Variations Granted | 297 | 80% |
| Utility Total Variations Granted | 2,011 | 74% |
| Highway Authority Total Variations Refused | 29 | 8% |
| Utility Total Variations Refused | 305 | 11% |
| Permit status | Number | Percentage |
|---|---|---|
| Highway Authority Total Permit Applications | 2,936 | 15% |
| Utility Total Permit Applications | 16,672 | 85% |
| Highway Authority Total Applications Granted | 2,274 | 77% |
| Utility Total Applications Granted | 13,255 | 79% |
| Highway Authority Total Applications Refused | 149 | 5% |
| Utility Total Applications Refused | 2,883 | 17% |
| Highway Authority Total Permit Variations | 221 | 6% |
| Utility Total Permit Variations | 3,398 | 94% |
| Highway Authority Total Variations Granted | 206 | 93% |
| Utility Total Variations Granted | 3,015 | 89% |
| Highway Authority Total Variations Refused | 12 | 5% |
| Utility Total Variations Refused | 318 | 9% |
| Permit status | Number | Percentage |
|---|---|---|
| Highway Authority Total Permit Applications | 4,664 | 29% |
| Utility Total Permit Applications | 11,600 | 71% |
| Highway Authority Total Applications Granted | 4,456 | 96% |
| Utility Total Applications Granted | 9,804 | 85% |
| Highway Authority Total Applications Refused | 458 | 10% |
| Utility Total Applications Refused | 1,577 | 14% |
| Highway Authority Total Permit Variations | 599 | 15% |
| Utility Total Permit Variations | 3,529 | 85% |
| Highway Authority Total Variations Granted | 572 | 95% |
| Utility Total Variations Granted | 3,215 | 91% |
| Highway Authority Total Variations Refused | 19 | 3% |
| Utility Total Variations Refused | 242 | 7% |
The number of permit and permit variation applications received, granted, refused and deemed by Promoter
| Promoter | Applications Received | Variations Received | Applications Granted | Variations Granted | Applications Refused | Variations Refused | Applications Deemed | Variations Deemed |
|---|---|---|---|---|---|---|---|---|
| Highway Authority | 2,869 | 372 | 2,577 | 297 | 277 | 29 | 14 | 4 |
| BT | 4,329 | 791 | 2,710 | 547 | 1,546 | 132 | 11 | 1 |
| CityFibre | 1,349 | 509 | 897 | 226 | 387 | 72 | 37 | 42 |
| Energy Assets Networks Ltd | 10 | 3 | 6 | 3 | 4 | |||
| EE | 148 | 20 | 71 | 18 | 73 | 2 | ||
| Euronetworks | 12 | 2 | 7 | 2 | 5 | |||
| Fulcrum Electrical Assets | 24 | 7 | 10 | 7 | 13 | |||
| Fulcrum Pipelines | 4 | 3 | 3 | 3 | 1 | |||
| Gas Transportation CP LTD | 58 | 19 | 31 | 18 | 26 | 1 | ||
| Harlaxton Energy Networks Limited | 7 | 1 | 6 | |||||
| Last Mile Electricity Limited | 30 | 8 | 15 | 8 | 12 | 1 | ||
| National Highways | 35 | 2 | 14 | 2 | 18 | |||
| Neoscorp Ltd | 29 | 4 | 14 | 3 | 15 | 1 | ||
| Network Rail | 39 | 12 | 30 | 11 | 7 | 1 | ||
| NWP Street Ltd | 45 | 10 | 27 | 10 | 16 | |||
| O2 Limited | 35 | 3 | 27 | 3 | 8 | |||
| Royal Mail Property & Facilities Solutions | 3 | 3 | ||||||
| Southern Gas Networks | 928 | 433 | 717 | 402 | 200 | 29 | 2 | |
| Southern Water | 7,180 | 369 | 6,222 | 359 | 666 | 9 | 13 | |
| UK Power Distribution Ltd | 2 | 6 | 2 | 2 | 4 | |||
| UK Power Networks South Eastern | 1,060 | 367 | 735 | 305 | 315 | 49 | 3 | 1 |
| Verizon Business | 1 | 1 | ||||||
| Virgin Media | 1,532 | 135 | 1,088 | 65 | 430 | 6 | 4 | |
| Vodafone | 44 | 17 | 23 | 17 | 21 | |||
| West Sussex County Council | 1 | 1 | ||||||
| Utility Total | 16,905 | 2,720 | 12,654 | 2,011 | 3,770 | 305 | 71 | 45 |
| Promoter | Applications Received | Variations Received | Applications Granted | Variations Granted | Applications Refused | Variations Refused | Applications Deemed | Variations Deemed |
|---|---|---|---|---|---|---|---|---|
| Highway Authority | 2,936 | 221 | 2,274 | 206 | 149 | 12 | 3 | 2 |
| Bournemouth, Christchurch and Poole Council | 2 | 2 | ||||||
| BT | 4,630 | 912 | 3,168 | 768 | 1,396 | 139 | 13 | 1 |
| CityFibre | 1,480 | 748 | 1,251 | 689 | 179 | 41 | 13 | 14 |
| Eclipse Power Networks | 24 | 38 | 13 | 31 | 9 | 7 | ||
| EE | 181 | 41 | 90 | 40 | 86 | |||
| Electricity Network Company Limited | 19 | 16 | 11 | 13 | 8 | 3 | ||
| Euronetworks | 5 | 5 | 5 | 5 | ||||
| Fulcrum Electrical Assets | 3 | 2 | 2 | 2 | 1 | |||
| Fulcrum Pipelines | 4 | 2 | 3 | 2 | 1 | |||
| Gas Transportation CP LTD | 8 | 3 | 5 | 1 | 2 | 2 | ||
| Global Reach Networks Ltd | 22 | 4 | 12 | 4 | 9 | |||
| Grain Communications Limited | 4 | 9 | 1 | 9 | 3 | |||
| Hutchinson 3G Limited | 16 | 6 | 5 | 6 | 11 | |||
| ITS Technology Group LTD | 44 | 22 | 30 | 19 | 13 | 2 | ||
| Last Mile Electricity Limited | 16 | 3 | 4 | 3 | 12 | |||
| MUA Electricity Ltd | 10 | 5 | 5 | 3 | 5 | 2 | ||
| National Highways | 60 | 5 | 43 | 5 | 15 | |||
| Neoscorp Ltd | 35 | 9 | 14 | 9 | 21 | |||
| Network Rail | 60 | 9 | 42 | 7 | 17 | |||
| NWP Street Ltd | 36 | 9 | 26 | 9 | 8 | - | - | - |
| O2 Limited | 35 | 11 | 11 | 11 | 22 | |||
| Open Fibre Networks | 5 | 1 | 2 | 1 | 3 | |||
| Royal Mail Property & Facilities Solutions | 3 | 3 | ||||||
| Southern Gas Networks | 787 | 304 | 607 | 265 | 168 | 29 | 9 | |
| Southern Water | 6,931 | 565 | 6,302 | 541 | 531 | 15 | 3 | |
| Surrey County Council | 2 | 2 | ||||||
| UK Power Networks South Eastern | 1,102 | 497 | 740 | 431 | 338 | 58 | 7 | 3 |
| Virgin Media | 1,130 | 161 | 848 | 139 | 16 | 20 | 1 | |
| Vodafone | 33 | 8 | 16 | 8 | 17 | |||
| West Sussex County Council | 1 | 1 | ||||||
| Utility Total | 16,672 | 3,389 | 13,255 | 3,015 | 2,883 | 318 | 46 | 18 |
| Promoter | Applications Received | Variations Received | Applications Granted | Variations Granted | Applications Refused | Variations Refused | Applications Deemed | Variations Deemed |
|---|---|---|---|---|---|---|---|---|
| Highway Authority | 4,664 | 599 | 4,456 | 572 | 458 | 19 | 16 | 4 |
| BT | 2,139 | 1,072 | 1,540 | 954 | 530 | 105 | 4 | 1 |
| CityFibre | 823 | 370 | 658 | 338 | 156 | 23 | 7 | 2 |
| Cornerstone | 10 | 1 | 3 | 1 | 7 | |||
| Eclipse Power Networks | 4 | 2 | 3 | 2 | ||||
| EE | 57 | 21 | 36 | 18 | 20 | 3 | ||
| Electricity Network Company Limited | 7 | 7 | 4 | 5 | 3 | 1 | ||
| Fulcrum Electrical Assets Limited | 10 | 6 | 7 | 6 | 1 | |||
| Gas Transportation CP LTD | 1 | |||||||
| Global Reach Networks Ltd | 55 | 29 | 38 | 27 | 17 | 2 | ||
| Grain Communications Limited | 109 | 88 | 74 | 81 | 33 | 6 | ||
| Hutchinson 3G Limited | 5 | 3 | 2 | |||||
| IPM Comms | 5 | 1 | 1 | 5 | ||||
| ITS Technology Group Ltd | 320 | 163 | 252 | 156 | 68 | 7 | ||
| MUA Electricity Ltd | 19 | 7 | 13 | 4 | 6 | 3 | ||
| National Highways | 44 | 15 | 38 | 15 | 4 | |||
| Last Mile Electricity Limited | 3 | 1 | 2 | 1 | 1 | |||
| Neoscorp Ltd | 8 | 1 | 6 | 1 | 2 | |||
| Network Rail | 33 | 5 | 29 | 3 | 1 | 2 | ||
| NWP Street Ltd | 28 | 9 | 20 | 9 | 7 | |||
| O2 Limited | 19 | 7 | 12 | 4 | 7 | 1 | ||
| Open Fibre Networks | 1 | 1 | ||||||
| UK Power Distribution Ltd | 6 | 1 | 3 | 1 | 3 | - | - | - |
| UK Power Networks South Eastern | 979 | 516 | 703 | 459 | 262 | 48 | 1 | |
| Royal Mail Property & Facilities Solutions | 2 | 1 | 2 | 1 | ||||
| Southern Gas Networks | 851 | 483 | 681 | 448 | 155 | 24 | 1 | |
| Southern Water | 5,333 | 721 | 5,062 | 680 | 190 | 17 | 7 | 1 |
| Virgin Media | 732 | 2 | 615 | 99 | 2 | |||
| Vodafone | 2 | 1 | ||||||
| Utility Total | 11,600 | 3,529 | 9,804 | 3,215 | 1,577 | 242 | 20 | 6 |
Permit and variation granted, number refused, deemed and cancelled for Category 0-2 and Traffic Sensitive Streets for Utility Works by Activity type
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 193 (7%) | 152 (20%) | 62 (8%) | ||||
| Major | 228 (9%) | 48 (6%) | 133 (28%) | 19 (32%) | 6 (32%) | 7 (88%) | 83 (11%) |
| Standard | 132 (5%) | 77 (10%) | 66 (14%) | 10 (17%) | 2 (11%) | 57 (7%) | |
| Minor | 1,487 (58%) | 451 (59%) | 178 (37%) | 18 (31%) | 11 (58%) | 1 (13%) | 549 (71%) |
| Immediate | 537 (21%) | 35 (5%) | 105 (22%) | 12 (20%) | 19 (2%) | ||
| Permit Variation | |||||||
| Total | 2,577 | 763 | 482 | 59 | 19 | 8 | 770 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 219(8%) | 119 (19%) | 3 (38%) | 57 (7%) | |||
| Major | 334 (12%) | 56 (9%) | 120 (19%) | 17 (23%) | 3 (38%) | 4 (80%) | 147 (19%) |
| Standard | 161 (6%) | 90 (14%) | 145 (23%) | 19 (26%) | 58 (7%) | ||
| Minor | 1,353 (49%) | 334 (52%) | 272 (43%) | 31 (42%) | 2 (25%) | 1 (20%) | 502 (64%) |
| Immediate | 708 (26%) | 40 (6%) | 95 (15%) | 7 (9%) | 25 (3%) | ||
| Permit Variation | |||||||
| Total | 2,775 | 639 | 632 | 74 | 8 | 5 | 789 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 36 (2%) | 37 (11%) | 17 (4%) | ||||
| Major | 62 (3%) | 10 (3%) | 44 (6%) | 3 (6%) | 18 (4%) | ||
| Standard | 175 (9%) | 76 (23%) | 149 (21%) | 13 (25%) | 1 (25%) | 1 (100%) | 67 (14%) |
| Minor | 1,056 (52%) | 173 (53%) | 384 (54%) | 29 (55%) | 3 (75%) | 353 (74%) | |
| Immediate | 720 (35%) | 32 (10%) | 130 (18%) | 8 (15%) | 20 (4%) | ||
| Permit Variation | |||||||
| Total | 2,049 | 328 | 707 | 53 | 4 | 1 | 475 |
Permit and variation granted, number refused, deemed and cancelled for Category 3-4 NON-TRAFFIC Sensitive Streets for Utility Works by Activity type
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 881 (9%) | 620 (21%) | 1 (2%) | 248 (9%) | |||
| Major | 1,115 (11%) | 209 (7%) | 472 (25%) | 86 (35%) | 18 (28%) | 28 (76%) | 323 (12%) |
| Standard | 530 (5%) | 379 (13%) | 301 (16%) | 39 (16%) | 5 (8%) | 4 (11%) | 177 (6%) |
| Minor | 5,769 (56%) | 1,656 (55%) | 681 (36%) | 84 (34%) | 38 (59%) | 3 (8%) | 1,984 (71%) |
| Immediate | 1,999 (19%) | 142 (5%) | 422 (22%) | 37 (15%) | 2 (3%) | 2 (5%) | 60 (2%) |
| Permit Variation | |||||||
| Total | 10,294 | 3,006 | 1,876 | 246 | 64 | 37 | 2,792 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 796 (8% ) | 486 (19% ) | 1 (<1% ) | 11 (29% ) | 231 (8% ) | ||
| Major | 1,346 (13% ) | 222 (9% ) | 446 (19% ) | 59 (24% ) | 9 (24% ) | 8 (62% ) | 546 (19% ) |
| Standard | 647 (6% ) | 341 (14% ) | 536 (22% ) | 58 (24% ) | 3 (8% ) | 2 (15% ) | 221 (8% ) |
| Minor | 5,059 (48% ) | 1,295 (52% ) | 994 (42% ) | 103 (42% ) | 12 (32% ) | 2 (15% ) | 1,854 (63% ) |
| Immediate | 2,634 (25% ) | 154 (6% ) | 409 (17% ) | 24 (10% ) | 3 (8% ) | 1 (8% ) | 80 (3% ) |
| Permit Variation | |||||||
| Total | 10,482 | 2,498 | 2,386 | 244 | 38 | 13 | 2,932 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 155 (2%) | 142 (11%) | 60 (3%) | ||||
| Major | 234 (3%) | 43 (3%) | 173 (6%) | 11 (6% ) | 2 (40%) | 72 (3%) | |
| Standard | 704 (9%) | 288 (23%) | 572 (21%) | 58 (31%) | 6 (46%) | 1 (20%) | 185 (9%) |
| Minor | 3,903 (50%) | 651 (52%) | 1,444 (54%) | 94 (50%) | 7 (54%) | 2 (40%) | 1,683 (82%) |
| Immediate | 2,762 (36%) | 128 (10%) | 490 (18%) | 24 (13%) | 59 (3%) | ||
| Permit Variation | |||||||
| Total | 7,758 | 1,252 | 2,679 | 187 | 13 | 5 | 2,059 |
The number of permit and permit variation granted, number refused, deemed and cancelled for Utility Works by Activity type
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 1,074 (8%) | 772 (20%) | 1 (1%) | 310 (9%) | |||
| Major | 1,343 (10%) | 257 (7%) | 605 (26%) | 105 (34%) | 24 (29%) | 35 (78%) | 406 (11%) |
| Standard | 662 (5%) | 456 (12%) | 367 (16%) | 49 (16%) | 7 (8%) | 4 (9%) | 234 (7%) |
| Minor | 7,256 (56%) | 2,107 (56%) | 859 (36%) | 102 (33%) | 49 (59%) | 4 (9%) | 2,533 (71%) |
| Immediate | 2,536 (20%) | 177 (5%) | 527 (22%) | 49 (16%) | 2 (2%) | 2 (4%) | 79 (2%) |
| Permit Variation | |||||||
| Total | 12,871 | 3,769 | 2,358 | 305 | 83 | 45 | 3,562 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 1,015 (8% ) | 605 (19% ) | 1 (<1% ) | 14 (30% ) | 288 (8% ) | ||
| Major | 1,680 (13% ) | 278 (9% ) | 566 (19% ) | 76 (24% ) | 12 (26% ) | 12 (67% ) | 693 (19% ) |
| Standard | 808 (6% ) | 431 (14% ) | 681 (23% ) | 77 (24% ) | 3 (7% ) | 2 (11% ) | 279 (7% ) |
| Minor | 6,412 (48% ) | 1,629 (52% ) | 1,266 (42% ) | 134 (42% ) | 14 (30% ) | 3 (17% ) | 2,356 (63% ) |
| Immediate | 3,342 (25% ) | 194 (6% ) | 504 (17% ) | 31 (10% ) | 3 (7% ) | 1 (6% ) | 105 (3% ) |
| Permit Variation | |||||||
| Total | 13,257 | 3,137 | 3,018 | 318 | 46 | 18 | 3,721 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 191 (2% ) | 179 (11% ) | 77 (3% ) | ||||
| Major | 296 (3% ) | 53 (3% ) | 217 (6% ) | 14 (6% ) | 2 (33% ) | 90 (4% ) | |
| Standard | 879 (9% ) | 364 (23% ) | 721 (21% ) | 71 (30% ) | 7 (41% ) | 2 (33% ) | 252 (10% ) |
| Minor | 4,959 (51% ) | 824 (52% ) | 1,828 (54% ) | 123 (51% ) | 10 (59% ) | 2 (33% ) | 2,036 (80% ) |
| Immediate | 3,482 (36% ) | 160 (10% ) | 620 (18% ) | 32 (13% ) | 79 (3% ) | ||
| Permit Variation | |||||||
| Total | 9,807 | 1,580 | 3,386 | 240 | 17 | 6 | 2,534 |
Permit and variation granted, number refused, deemed and cancelled for Category 0-2 and Traffic Sensitive Streets for Highway Works by Activity type
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 41 (7% ) | 10 (18% ) | 3 (100% ) | 1 (5% ) | |||
| Major | 49 (8% ) | 8 (14% ) | 35 (45% ) | 5 (83% ) | 1 (100% ) | 3 (15% ) | |
| Standard | 87 (15% ) | 11 (19% ) | 25 (32% ) | 1 (17% ) | 10 (50% ) | ||
| Minor | 65 (11% ) | 14 (25% ) | 11 (14% ) | 4 (20% ) | |||
| Immediate | 336 (58% ) | 14 (25% ) | 6 (8% ) | 2 (10% ) | |||
| Permit Variation | |||||||
| Total | 578 | 57 | 77 | 6 | 3 | 1 | 20 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 20 (3% ) | 4 (15% ) | |||||
| Major | 28 (4% ) | 3 (12% ) | 18 (40% ) | 2 (100% ) | |||
| Standard | 70 (11% ) | 4 (15% ) | 15 (33% ) | 8 (53% ) | |||
| Minor | 56 (8% ) | 5 (19% ) | 7 (16% ) | 3 (20% ) | |||
| Immediate | 487 (74% ) | 10 (38% ) | 5 (11% ) | 4 (27% ) | |||
| Permit Variation | |||||||
| Total | 661 | 26 | 45 | 2 | 15 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 29 (3% ) | 11 (32% ) | 6 (14% ) | ||||
| Major | 35 (4% ) | 4 (12% ) | 24 (18% ) | 1 (25% ) | 2 (67% ) | 4 (9% ) | |
| Standard | 84 (9% ) | 5 (15% ) | 34 (26% ) | 3 (75% ) | 8 (18% ) | ||
| Minor | 261 (29% ) | 7 (21% ) | 63 (47% ) | 1 (33% ) | 20 (45% ) | ||
| Immediate | 502 (55% ) | 7 (21% ) | 12 (9% ) | 6 (14% ) | |||
| Permit Variation | |||||||
| Total | 911 | 34 | 133 | 4 | 3 | 44 |
Permit and variation granted, number refused, deemed and cancelled for Category 3-4 Non Traffic Sensitive Streets for Highway Works by Activity type
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 169 (7% ) | 47 (17% ) | 1 (<1% ) | 11 (73% ) | 6 (6% ) | ||
| Major | 188 (7% ) | 43 (16% ) | 156 (46% ) | 19 (66% ) | 2 (13% ) | 3 (75% ) | 16 (17% ) |
| Standard | 373 (14% ) | 50 (18% ) | 112 (33% ) | 5 (17% ) | 1 (7% ) | 51 (54% ) | |
| Minor | 250 (10% ) | 62 (23% ) | 47 (14% ) | 3 (10% ) | 1 (7% ) | 16 (17% ) | |
| Immediate | 1,597 (62% ) | 69 (25% ) | 23 (7% ) | 2 (7% ) | 1 (25% ) | 6 (6% ) | |
| Permit Variation | |||||||
| Total | 2,577 | 271 | 339 | 29 | 15 | 4 | 95 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 72 (3% ) | 23 (19% ) | 4 (8% ) | ||||
| Major | 90 (4% ) | 18 (15% ) | 63 (39% ) | 7 (70% ) | 2 (100% ) | 1 (2% ) | |
| Standard | 221 (10% ) | 19 (15% ) | 57 (35% ) | 3 (30% ) | 29 (58% ) | ||
| Minor | 165 (8% ) | 15 (12% ) | 24 (15% ) | 1 (33% ) | 8 (16% ) | ||
| Immediate | 1,565 (74% ) | 49 (40% ) | 17 (11% ) | 2 (67% ) | 8 (16% ) | ||
| Permit Variation | |||||||
| Total | 2,113 | 124 | 161 | 10 | 3 | 2 | 50 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 123 (3% ) | 38 (31% ) | 1 (<1% ) | 3 (23% ) | 23 (14% ) | ||
| Major | 133 (4% ) | 12 (10% ) | 91 (19% ) | 6 (40% ) | 4 (31% ) | 3 (75% ) | 14 (9% ) |
| Standard | 299 (8% ) | 20 (16% ) | 133 (28% ) | 8 (53% ) | 1 (25% ) | 29 (18% ) | |
| Minor | 1,053 (30% ) | 25 (20% ) | 204 (43% ) | 1 (7% ) | 3 (23% ) | 74 (47% ) | |
| Immediate | 1,937 (55% ) | 28 (23% ) | 49 (10% ) | 3 (23% ) | 19 (12% ) | ||
| Permit Variation | |||||||
| Total | 3,545 | 123 | 478 | 15 | 13 | 4 | 159 |
The number of permit and permit variation granted, number refused, deemed and cancelled for Highway Works by Activity type
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 210 (7% ) | 57 (17% ) | 1 (<1% ) | 14 (78% ) | 7 (6% ) | ||
| Major | 237 (8% ) | 51 (16% ) | 191 (46% ) | 24 (69% ) | 2 (11% ) | 4 (80% ) | 19 (17% ) |
| Standard | 460 (15% ) | 61 (19% ) | 137 (33% ) | 6 (17% ) | 1 (6% ) | 61 (53% ) | |
| Minor | 315 (10% ) | 76 (23% ) | 58 (14% ) | 3 (9% ) | 1 (6% ) | 20 (17% ) | |
| Immediate | 1,933 (61% ) | 83 (25% ) | 29 (7% ) | 2 (6% ) | 1 (20% ) | 8 (7% ) | |
| Permit Variation | |||||||
| Total | 3,155 | 328 | 416 | 35 | 18 | 5 | 115 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 92 (3% ) | 27 (18% ) | 4 (6% ) | ||||
| Major | 118 (4% ) | 21 (14% ) | 81 (39% ) | 9 (75% ) | 2 (100% ) | 1 (2% ) | |
| Standard | 291 (10% ) | 23 (15% ) | 72 (35% ) | 3 (25% ) | 37 (57% ) | ||
| Minor | 221 (8% ) | 20 (13% ) | 31 (15% ) | 1 (33% ) | 11 (17% ) | ||
| Immediate | 2,052 (74% ) | 59 (39% ) | 22 (11% ) | 2 (67% ) | 12 (18% ) | ||
| Permit Variation | |||||||
| Total | 2,774 | 150 | 206 | 12 | 3 | 2 | 65 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 152 (3% ) | 49 (31% ) | 1 (<1% ) | 3 (19% ) | 29 (14% ) | ||
| Major | 168 (4% ) | 16 (10% ) | 115 (19% ) | 7 (37% ) | 6 (38% ) | 3 (75% ) | 18 (9% ) |
| Standard | 383 (9% ) | 25 (16% ) | 167 (27% ) | 11 (58% ) | 1 (25% ) | 37 (18% ) | |
| Minor | 1,314 (29% ) | 32 (20% ) | 267 (44% ) | 1 (5% ) | 4 (25% ) | 94 (46% ) | |
| Immediate | 2,439 (55% ) | 35 (22% ) | 61 (10% ) | 3 (19% ) | 25 (12% ) | ||
| Permit Variation | |||||||
| Total | 4,456 | 157 | 611 | 19 | 16 | 4 | 203 |
Permit and variation granted, number refused, deemed and cancelled for Category 0-2 and Traffic Sensitive Streets for All Works by Activity type
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 234 (7% ) | 162 (20% ) | 3 (14% ) | 63 (8% ) | |||
| Major | 277 (9% ) | 56 (7% ) | 168 (30% ) | 24 (37% ) | 6 (27% ) | 8 (89% ) | 86 (11% ) |
| Standard | 219 (7% ) | 88 (11% ) | 91 (16% ) | 11 (17% ) | 2 (9% ) | 67 (8% ) | |
| Minor | 1,552 (49% ) | 465 (57% ) | 189 (34% ) | 18 (28% ) | 11 (50% ) | 1 (11% ) | 553 (70% ) |
| Immediate | 873 (28% ) | 49 (6% ) | 111 (20% ) | 12 (18% ) | 21 (3% ) | ||
| Permit Variation | |||||||
| Total | 3,155 | 820 | 559 | 65 | 22 | 9 | 790 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 239 (7% ) | 123 (18% ) | 3 (38% ) | 57 (7% ) | |||
| Major | 362 (11% ) | 59 (9% ) | 138 (20% ) | 19 (25% ) | 3 (38% ) | 4 (80% ) | 147 (18% ) |
| Standard | 231 (7% ) | 94 (14% ) | 160 (24% ) | 19 (25% ) | 66 (8% ) | ||
| Minor | 1,409 (41% ) | 339 (51% ) | 279 (41% ) | 31 (41% ) | 2 (25% ) | 1 (20% ) | 505 (63% ) |
| Immediate | 1,195 (35% ) | 50 (8% ) | 100 (15% ) | 7 (9% ) | 29 (4% ) | ||
| Permit Variation | |||||||
| Total | 3,436 | 665 | 677 | 76 | 8 | 5 | 804 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 65 (2% ) | 48 (13% ) | 23 (4% ) | ||||
| Major | 97 (3% ) | 14 (4% ) | 68 (8% ) | 4 (7% ) | 2 (29% ) | 22 (4% ) | |
| Standard | 259 (9% ) | 81 (22% ) | 183 (22% ) | 16 (28% ) | 1 (14% ) | 1 (100% ) | 75 (14% ) |
| Minor | 1,317 (44% ) | 180 (50% ) | 447 (53% ) | 29 (51% ) | 4 (57% ) | 373 (72% ) | |
| Immediate | 1,222 (41% ) | 39 (11% ) | 142 (17% ) | 8 (14% ) | 26 (5% ) | ||
| Permit Variation | |||||||
| Total | 2,960 | 362 | 840 | 57 | 7 | 1 | 519 |
Permit and variation granted, number refused, deemed and cancelled for Category 3-4 NON-TRAFFIC Sensitive Streets for All Works by Activity type
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 1,050 (8% ) | 667 (20% ) | 1 (<1% ) | 12 (15% ) | 254 (9% ) | ||
| Major | 1,303 (10% ) | 252 (8% ) | 628 (28% ) | 105 (38% ) | 20 (25% ) | 31 (76% ) | 339 (12% ) |
| Standard | 903 (7% ) | 429 (13% ) | 413 (19% ) | 44 (16% ) | 6 (8% ) | 4 (10% ) | 228 (8% ) |
| Minor | 6,019 (47% ) | 1,718 (52% ) | 728 (33% ) | 87 (32% ) | 39 (49% ) | 3 (7% ) | 2,000 (69% ) |
| Immediate | 3,596 (28% ) | 211 (6% ) | 445 (20% ) | 39 (14% ) | 2 (3% ) | 3 (7% ) | 66 (2% ) |
| Permit Variation | |||||||
| Total | 12,871 | 3,277 | 2,215 | 275 | 79 | 41 | 2,887 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 868 (7% ) | 509 (19% ) | 1 (<1% ) | 11 (27% ) | 235 (8% ) | ||
| Major | 1,436 (11% ) | 240 (9% ) | 509 (20% ) | 66 (26% ) | 9 (22% ) | 10 (67% ) | 547 (18% ) |
| Standard | 868 (7% ) | 360 (14% ) | 593 (23% ) | 61 (24% ) | 3 (7% ) | 2 (13% ) | 250 (8% ) |
| Minor | 5,224 (41% ) | 1,310 (50% ) | 1,018 (40% ) | 103 (41% ) | 13 (32% ) | 2 (13% ) | 1,862 (62% ) |
| Immediate | 4,199 (33% ) | 203 (8% ) | 426 (17% ) | 24 (9% ) | 5 (12% ) | 1 (7% ) | 88 (3% ) |
| Permit Variation | |||||||
| Total | 12,595 | 2,622 | 2,547 | 254 | 41 | 15 | 2,982 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 288 (2% ) | 154 (11% ) | 91 (3% ) | 6 (3% ) | 4 (11% ) | 3 (23% ) | 74 (3% ) |
| Major | 533 (4% ) | 63 (4% ) | 306 (8% ) | 19 (9% ) | 3 (23% ) | 101 (4% ) | |
| Standard | 1,757 (12% ) | 313 (21% ) | 776 (21% ) | 59 (27% ) | 9 (25% ) | 1 (8% ) | 259 (11% ) |
| Minor | 5,840 (40% ) | 679 (47% ) | 1,493 (41% ) | 94 (43% ) | 10 (28% ) | 2 (15% ) | 1,702 (72% ) |
| Immediate | 2,762 (19% ) | 128 (9% ) | 490 (13% ) | 24 (11% ) | 59 (3% ) | ||
| Permit Variation | 3,545 (24%) | 123 (8%) | 478 (13%) | 15 (7%) | 13 (36%) | 4 (31%) | 159 (7%) |
| Total | 14,725 | 1,460 | 3,634 | 217 | 36 | 13 | 2,354 |
The number of permit and permit variation granted, number refused, deemed superseded and cancelled for All Works by Activity type
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 1,284 (8% ) | 829 (20% ) | 1 (<1% ) | 15 (15% ) | 317 (9% ) | ||
| Major | 1,580 (10% ) | 308 (8% ) | 796 (29% ) | 129 (38% ) | 26 (26% ) | 39 (78% ) | 425 (12% ) |
| Standard | 1,122 (7% ) | 517 (13% ) | 504 (18% ) | 55 (16% ) | 8 (8% ) | 4 (8% ) | 295 (8% ) |
| Minor | 7,571 (47% ) | 2,183 (53% ) | 917 (33% ) | 105 (31% ) | 50 (50% ) | 4 (8% ) | 2,553 (69% ) |
| Immediate | 4,469 (28% ) | 260 (6% ) | 556 (20% ) | 51 (15% ) | 2 (2% ) | 3 (6% ) | 87 (2% ) |
| Permit Variation | |||||||
| Total | 16,026 | 4,097 | 2,774 | 340 | 101 | 50 | 3,677 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 1,107 (7% ) | 632 (19% ) | 1 (<1% ) | 14 (29% ) | 292 (8% ) | ||
| Major | 1,798 (11% ) | 299 (9% ) | 647 (20% ) | 85 (26% ) | 12 (24% ) | 14 (70% ) | 694 (18% ) |
| Standard | 1,099 (7% ) | 454 (14% ) | 753 (23% ) | 80 (24% ) | 3 (6% ) | 2 (10% ) | 316 (8% ) |
| Minor | 6,633 (41% ) | 1,649 (50% ) | 1,297 (40% ) | 134 (41% ) | 15 (31% ) | 3 (15% ) | 2,367 (63% ) |
| Immediate | 5,394 (34% ) | 253 (8% ) | 526 (16% ) | 31 (9% ) | 5 (10% ) | 1 (5% ) | 117 (3% ) |
| Permit Variation | |||||||
| Total | 16,031 | 3,287 | 3,224 | 330 | 49 | 20 | 3,786 |
| Activity Type | Permit App Granted | Permit App Refused | Variation Granted | Variation Refused | Deemed Permit Applications | Deemed Permit Variations | Cancelled /Aborted |
|---|---|---|---|---|---|---|---|
| Provisional Advance | 353 (2% ) | 202 (11% ) | 91 (2% ) | 6 (2% ) | 4 (9% ) | 3 (21% ) | 97 (3% ) |
| Major | 630 (4% ) | 77 (4% ) | 374 (8% ) | 23 (8% ) | 2 (5% ) | 3 (21% ) | 123 (4% ) |
| Standard | 2,016 (11% ) | 394 (22% ) | 959 (21% ) | 75 (27% ) | 10 (23% ) | 2 (14% ) | 334 (12% ) |
| Minor | 7,157 (40% ) | 859 (47% ) | 1,940 (43% ) | 123 (45% ) | 14 (33% ) | 2 (14% ) | 2,075 (72% ) |
| Immediate | 3,984 (23% ) | 167 (9% ) | 632 (14% ) | 32 (12% ) | 85 (3% ) | ||
| Permit Variation | 3,545 (20%) | 123 (7%) | 478 (11%) | 15 (5%) | 13 (30%) | 4 (29%) | 159 (6%) |
| Total | 17,685 | 1,822 | 4,474 | 274 | 43 | 14 | 2,873 |
Appendix 2: KPI 2 - Number of conditions applied by condition type
Conditions are attached to applications by the Works Promoter or when requested by the Permit Authority and help deliver the Permit Scheme objectives and societal benefits.
| Condition Type | Utility Works | Highway Authority Works | Total |
|---|---|---|---|
| Date Constraints | 16,905 | 2,869 | 19,774 |
| Time Constraints | 7,461 | 600 | 8,061 |
| Out of Hours Work | 80 | 4 | 84 |
| Material and Plant Storage | 1,858 | 11 | 1,869 |
| Road Occupation Dimensions | 1,448 | 78 | 1,526 |
| Traffic Space Dimensions | 4,364 | 39 | 4,403 |
| Road Closure | 674 | 263 | 937 |
| Light Signals and Shuttle Working | 3,570 | 397 | 3,967 |
| Traffic Management Changes | 3,123 | 284 | 3,407 |
| Work Methodology | 1,815 | 258 | 2,073 |
| Consultation and Publicity | 16,905 | 2,869 | 19,774 |
| Environmental | 475 | 19 | 494 |
| Local | 1,215 | 22 | 1,237 |
| Total | 59,893 | 7,713 | 67,606 |
| Condition Type | Utility Works | Highway Authority Works | Total |
|---|---|---|---|
| Date Constraints | 16,688 | 2,936 | 19,624 |
| Time Constraints | 7,260 | 293 | 7,553 |
| Out of Hours Work | 59 | 3 | 62 |
| Material and Plant Storage | 1,493 | 15 | 1,508 |
| Road Occupation Dimensions | 916 | 6 | 922 |
| Traffic Space Dimensions | 3,884 | 18 | 3,902 |
| Road Closure | 791 | 98 | 889 |
| Light Signals and Shuttle Working | 4,198 | 253 | 4,451 |
| Traffic Management Changes | 3,622 | 254 | 3,876 |
| Work Methodology | 1,481 | 144 | 1,625 |
| Consultation and Publicity | 16,688 | 2,936 | 19,624 |
| Environmental | 188 | 16 | 204 |
| Local | 638 | 22 | 660 |
| Total | 57,906 | 6,994 | 64,900 |
| Condition Type | Utility Works | Highway Authority Works | Total |
|---|---|---|---|
| Date Constraints | 11,616 | 4,664 | 16,280 |
| Time Constraints | 3,200 | 559 | 3,759 |
| Out of Hours Work | 42 | 16 | 58 |
| Material and Plant Storage | 743 | 12 | 755 |
| Road Occupation Dimensions | 658 | 51 | 709 |
| Traffic Space Dimensions | 2,147 | 91 | 2,238 |
| Road Closure | 507 | 247 | 754 |
| Light Signals and Shuttle Working | 1,518 | 318 | 1,836 |
| Traffic Management Changes | 1,341 | 486 | 1,827 |
| Work Methodology | 905 | 89 | 994 |
| Consultation and Publicity | 11,616 | 4,664 | 16,280 |
| Environmental | 165 | 38 | 203 |
| Local | 131 | 13 | 144 |
| Total | 34,589 | 11,248 | 45,837 |
Appendix 2: KPI 3 - Number of approved extensions
| Month | Highway Authority | Utilities | Total |
|---|---|---|---|
| April | 15 | 69 | 84 |
| May | 13 | 69 | 82 |
| June | 15 | 79 | 94 |
| July | 24 | 67 | 91 |
| August | 12 | 70 | 82 |
| September | 13 | 76 | 89 |
| October | 14 | 61 | 75 |
| November | 26 | 63 | 89 |
| December | 12 | 65 | 77 |
| January | 10 | 66 | 76 |
| February | 11 | 77 | 88 |
| March | |||
| Total | 165 | 762 | 927 |
| Month | Highway Authority | Utilities | Total |
|---|---|---|---|
| April | 15 | 42 | 57 |
| May | 7 | 54 | 61 |
| June | 5 | 58 | 63 |
| July | 12 | 69 | 81 |
| August | 11 | 66 | 77 |
| September | 5 | 73 | 78 |
| October | 5 | 89 | 94 |
| November | 12 | 61 | 73 |
| December | 22 | 36 | 58 |
| January | 4 | 96 | 100 |
| February | 5 | 51 | 56 |
| March | 18 | 38 | 56 |
| Total | 121 | 733 | 854 |
| Month | Highway Authority | Utilities | Total |
|---|---|---|---|
| April | 4 | 77 | 81 |
| May | 2 | 39 | 41 |
| June | 7 | 62 | 69 |
| July | 6 | 75 | 81 |
| August | 12 | 67 | 79 |
| September | 8 | 59 | 67 |
| October | 13 | 65 | 78 |
| November | 33 | 74 | 107 |
| December | 13 | 35 | 48 |
| January | 20 | 47 | 67 |
| February | 21 | 64 | 85 |
| March | 9 | 56 | 65 |
| Total | 148 | 720 | 868 |
Appendix 2: KPI 7 - Number of inspections carried out to monitor conditions
This KPI is broken down by promoter and shown as the number of sample permit condition checks carried out as a percentage of those issued.
| Promoter | Passed | Non-Compliant | Total inspections |
|---|---|---|---|
| Highway Authority | 31 | 11 | 42 |
| BT | 1,256 | 256 | 1,512 |
| CityFibre | 412 | 363 | 775 |
| EE | 69 | 17 | 86 |
| Energy Asset Networks Limited | 12 | 3 | 15 |
| Euronetworks | 10 | 10 | 20 |
| Fulcrum Electrical Assets | 12 | 7 | 19 |
| Fulcrum Pipelines | 6 | 6 | |
| Gas Transportation CP LTD | 16 | 2 | 18 |
| Last Mile Electricity Limited | 11 | 11 | |
| MUA Electricity Ltd | |||
| Neoscorp Ltd | 27 | 3 | 30 |
| NWP Street Ltd | 1 | 1 | |
| O2 Limited | 16 | 3 | 19 |
| Open Fibre Networks | |||
| Royal Mail Property & Facilities Solutions | 4 | 4 | |
| Southern Gas Networks | 960 | 59 | 1,019 |
| Southern Water | 4,916 | 162 | 5,078 |
| UK Power Networks South Eastern | 771 | 45 | 816 |
| Verizon Business | 1 | 1 | |
| Virgin Media | 842 | 64 | 906 |
| Vodafone | 20 | 6 | 26 |
| Utility Total | 9,362 | 1,000 | 10,362 |
| Promoter | Passed | Non-Compliant | Total inspections |
|---|---|---|---|
| Highway Authority | 44 | 5 | 49 |
| BT | 2,044 | 1,057 | 3,101 |
| CityFibre | 546 | 1,544 | 2,090 |
| EE | 80 | 10 | 90 |
| Energy Asset Networks Limited | 14 | 14 | |
| Euronetworks | 21 | 8 | 29 |
| Fulcrum Electrical Assets | 7 | 1 | 8 |
| Fulcrum Pipelines | 5 | 5 | |
| Gas Transportation CP LTD | 17 | 17 | |
| Grain Communications Limited | 2 | 1 | 3 |
| ITS Technology Group LTD | 1 | 1 | |
| Last Mile Electricity Limited | 20 | 20 | |
| MUA Electricity Ltd | 2 | 1 | 3 |
| Neoscorp Ltd | 7 | 7 | |
| NWP Street Ltd | 1 | 1 | |
| O2 Limited | 18 | 18 | |
| Royal Mail Property & Facilities Solutions | 6 | 6 | |
| Southern Gas Networks | 1,073 | 263 | 1,336 |
| Southern Water | 8,595 | 335 | 8,930 |
| UK Power Networks South Eastern | 1,169 | 86 | 1,255 |
| Virgin Media | 1,301 | 134 | 1,435 |
| Vodafone | 19 | 2 | 21 |
| Utility Total | 14,947 | 3,443 | 18,390 |
| Promoter | Passed | Non-Compliant | Total inspections |
|---|---|---|---|
| Highway Authority | 17 | 16 | 33 |
| BT | 561 | 180 | 741 |
| CityFibre | 460 | 647 | 1,107 |
| Cornerstone Telecommunications Infrastructure Limited | 2 | 2 | |
| Eclipse Power Networks Limited | 4 | 4 | |
| EE | 16 | 3 | 19 |
| Electricity Network Company Limited | 4 | 7 | 11 |
| Euronetworks | 1 | 1 | |
| Gas Transportation CP LTD | 2 | 2 | |
| Global Reach Networks Ltd | 15 | 7 | 22 |
| Grain Communications Limited | 29 | 30 | 59 |
| Hutchinson 3G Limited | 4 | 4 | |
| ITS Technology Group LTD | 77 | 47 | 124 |
| Last Mile Electricity Limited | 1 | 1 | |
| MUA Electricity Ltd | 10 | 1 | 11 |
| Neoscorp Ltd | 6 | 6 | |
| NWP Street Ltd | 16 | 3 | 19 |
| O2 Limited | 12 | 12 | |
| Open Fibre Networks | 3 | 3 | |
| Royal Mail Property & Facilities Solutions | 2 | 2 | |
| Southern Gas Networks | 397 | 384 | 781 |
| Southern Water | 2,775 | 322 | 3,097 |
| UK Power Networks South Eastern | 401 | 40 | 441 |
| Verizon Business | 1 | 2 | 3 |
| Virgin Media | 227 | 46 | 273 |
| Vodafone | 2 | - | 2 |
| West Sussex County Council | |||
| Utility Total | 5,028 | 1,719 | 6,747 |
Appendix 2: HAUC TPI measures
Table 17 TPI 1 Works Phases Started (Base Data) by Promoter.
This data is not available from the IT system at this time.
Table 18 TPI 1 Works Phases Started (Base Data) For Highway Authority Works.
This data is not available from the IT system at this time.
Table 19 TPI 1 Works Phases Started (Base Data) For Utility Works.
This data is not available from the IT system at this time.
Table 20 TPI 2 Works Phases Completed (Base Data) by Promoter.
This data is not available from the IT system at this time.
Table 21 TPI 2 Works Phases Completed (Base Data) for Highway Authority Works by Reinstatement Category.
This data is not available from the IT system at this time.
Table 22 TPI 2 Works Phases Completed (Base Data) for Utility Works by Reinstatement Category
This data is not available from the IT system at this time.
Table 23 TPI 3 Days Of Occupancy Phases Completed by Promoter
This data is not available from the IT system at this time.
Table 24 TPI 3 Days Of Occupancy Phases Completed for Highway Authority Works by Reinstatement Category and Traffic Sensitivity.
This data is not available from the IT system at this time.
Table 25 TPI 3 Days Of Occupancy Phases Completed for Utility Works by Reinstatement Category and Traffic Sensitivity.
This data is not available from the IT system at this time.
| Works Type | Highway Authority | Utility |
|---|---|---|
| Major | 13 | 7 |
| Standard | 6 | 5 |
| Minor | 2 | 2 |
| Immediate-Urgent | 2 | 3 |
| Immediate-Emergency | 1 | 5 |
| Works Type | Highway Authority | Utility |
|---|---|---|
| Major | 14 | 5 |
| Standard | 6 | 6 |
| Minor | 2 | 2 |
| Immediate-Urgent | 2 | 3 |
| Immediate-Emergency | 1 | 5 |
Table 26(C) TPI 4 Average Duration of Works Phases Completed. Year 9
This data is not available from the IT system at this time.
| Works Type | Major | Standard | Minor | Urgent | Emergency | Total |
|---|---|---|---|---|---|---|
| All Promoters | 3,873 | 1,559 | 6,768 | 3,758 | 611 | 16,569 |
| Highway Authority | 451 | 433 | 314 | 1,590 | 74 | 2,862 |
| Utilities | 3,422 | 1,126 | 6,454 | 2,168 | 537 | 13,707 |
| Works Type | Major | Standard | Minor | Urgent | Emergency | Total |
|---|---|---|---|---|---|---|
| All Promoters | 3,865 | 1,536 | 8,410 | 4,881 | 763 | 19,455 |
| Highway Authority | 260 | 315 | 244 | 1,887 | 221 | 2,927 |
| Utilities | 3,605 | 1,221 | 8,166 | 2,994 | 542 | 16,528 |
| Works Type | Major | Standard | Minor | Urgent | Emergency | Total |
|---|---|---|---|---|---|---|
| All Promoters | 1,139 | 1,664 | 7,272 | 5,568 | 550 | 16,193 |
| Highway Authority | 399 | 412 | 1,366 | 2,400 | 76 | 4,653 |
| Utilities | 740 | 1,252 | 5,906 | 3,168 | 474 | 11,540 |
| Highway Authority | 14 |
|---|---|
| Utility | 73 |
| Highway Authority | 3 |
|---|---|
| Utility | 46 |
| Highway Authority | 16 |
|---|---|
| Utility | 22 |
Table 29 TPI 7 Number of Phase One Permanent Registrations.
This data is not available from the IT system at this time.
Table 30 TPI7 Number of Phase One Permanent Registrations for Highway Authority Works by Reinstatement Category and Traffic Sensitivity Street.
This data is not available from the IT system at this time.
Table 31 TPI7 Number of Phase One Permanent Registrations for Utility Works by Reinstatement Category and Traffic Sensitivity Street.
This data is not available from the IT system at this time.
| Year 7 | 2,145 |
|---|---|
| Year 8 | 1,794 |
| Year 9 | 596 |
| Year 7 | 1,243 |
|---|---|
| Year 8 | 1,108 |
| Year 9 | 344 |
| Year 7 | 11 |
|---|---|
| Year 8 | 14 |
| Year 9 | 3 |
| Year 7 | 19,774 |
|---|---|
| Year 8 | 19,624 |
| Year 9 | 16,280 |
Table 36 Number of Permit applications granted on first application submission
This data is not available from the IT system at this time.
Table 37 Number of “modified” applications submitted prior to Permit being granted or deemed
This data is not available from the IT system at this time.
| Year 7 | 85 |
|---|---|
| Year 8 | 49 |
| Year 9 | 36 |
| Year 7 | 228 |
|---|---|
| Year 8 | 216 |
| Year 9 | 124 |
| Year 7 | 3,236 |
|---|---|
| Year 8 | 3,557 |
| Year 9 | 1,902 |
| Year 7 | 28 |
|---|---|
| Year 8 | 57 |
| Year 9 | 75 |
Table 42 Number of Duration variations after works started
This data is not available from the IT system at this time.
| Year 7 | 117 |
|---|---|
| Year 8 | 260 |
| Year 9 | 67 |
| Year 7 | 122 |
|---|---|
| Year 8 | 112 |
| Year 9 | 104 |
Appendix 3: Income and costs
Fee income
This permit scheme evaluation report covers the period from the 1st April 2021 to the 31st March 2024 inclusive.
£836,797 of Permit and Permit Variation fee income was received over the 12 months in year 7 1st April 2021 to the 31st March 2022.
£828,129 of Permit and Permit Variation fee income was received over the 12 months in year 8 1st April 2022 to the 31st March 2023.
£634,450 of Permit and Permit Variation fee income was received over the 12 months in year 9 1st April 2023 to the 31st March 2024.
Total fee income is decreasing due to the decreasing number of permit applications.
Costs budgets and actuals
Over the 3 years a total of £2,299,375 of Permit fee income was received and costs totalled £2,452,859.
As total fee income is less than total costs over the 3-year period, no consideration will be given changing Permit fees in 2024/25.
Over the next 3 to 5 years a loss position is expected to continue to develop unless costs can be reduced.
| Operational Cost | Year 7 | Year 8 | Year 9 |
|---|---|---|---|
| KPI Production | £21,000 | ||
| IT support | £109,400 | £91,518 | £101,091 |
| Management Overhead | £30,250 | £29,080 | £25,880 |
| Training | £534 | £0 | £1,659 |
| Staff | £634,608 | £687,907 | £719,932 |
| Totals | £774,792 | £829,505 | £848,562 |
Appendix 3: Average permit cost and cost benefit analysis
By dividing the number of Utility Permits granted by the Permit Scheme cost an average cost per Permit can be calculated.
This is a useful indicator of the general scheme costs to Utilities and can be compared to other schemes to show a general financial efficiency level.
Average Permit Cost
Year 7
- Total Utility Permit Applications - 19,774
- Total Scheme Cost - £774,792
- Average Permit Cost - £39
Year 8
- Total Utility Permit Applications - 19,608
- Total Scheme Cost - £829,505
- Average Permit Cost - £42
Year 9
- Total Utility Permit Applications - 16,264
- Total Scheme Cost - £848,562
- Average Permit Cost - £52
Highway Authority Cost Benefit results. 5% reduction in works impact
Year 7
- Costs - £774,792
- Benefit - £8,437,974
- Benefit to Cost Ratio - 10.89:1
Year 8
- Costs - £829,505
- Benefit - £8,603,066
- Benefit to Cost Ratio - 10.37:1
Year 9
- Costs - £848,562
- Benefit - £7,900,040
- Benefit to Cost Ratio - 9.31:1