Major repair work at the King Alfred Leisure Centre is progressing well with two of the three boilers now up and running and providing hot water to most of the building, including the sinks and showers.
A new control panel has been fitted, re-wiring completed and the process of reheating the swimming pools has begun.
However, this has to be done slowly so it will be several weeks before the water reaches the correct temperature for swimming.
While the building has been closed, we are pleased to have carried out further improvements around the centre which include decorating several areas and refurbishing the ballroom dance floor.
We are still aiming to re-open the centre in time for Easter.