Work to support the development of the Big Yellow Storage site on Old Shoreham Road is set to begin from Monday 28 June.
The work to connect the development at the junction of Holmes Avenue to the sewer network means it will be necessary to close part of the road, cycle lane and pedestrian footway in three stages.
Once each stage is completed, the road will be returned to normal until the next stage begins.
The work, which is being carried out by the developer, will be done as follows:
Beginning 28 June
Work on the westbound traffic lane, meaning traffic will merge with the current cycle lane. Pedestrians will continue to use the footway.
Beginning 5 July
Work on the cycle lane, meaning cyclists will merge with traffic on the westbound traffic lane. Pedestrians will continue to use the footway.
Beginning 12 July
Work on the pedestrian footway. Pedestrians will be redirected onto the cycle lane and cyclists will merge with traffic on the westbound traffic lane.
We apologise for the inconvenience while this work is carried out.